    "dataset": "Ogbaru projects",
    "source": "Research dossier (29 Sep 2026), sections 7 and 8, and the sources named in each row.",
    "licence": {
        "name": "CC BY 4.0",
        "url": "https://creativecommons.org/licenses/by/4.0/"
    },
    "updated": "2026-10-01",
    "projects": [
        {
            "slug": "okpoko-roads",
            "title": "Okpoko urban regeneration roads",
            "type": "road",
            "project_status": "ongoing",
            "status_note": "As at March 2025: 15.62 km complete, 3.46 km under construction",
            "funder": "Anambra State Government",
            "cost_ngn": 9000000000,
            "cost_note": "N9 billion approved in August 2022. Final cost not reported.",
            "start_date": null,
            "target_date": null,
            "completed_date": null,
            "ward_code": null,
            "description": "Dual-carriageway roads with drainage, planned at roughly 14 km when approved. 12 km was commissioned in March 2024. A June 2026 press feature says over 14 roads have been rehabilitated. Streetlights, water supply and a general hospital followed. Totals are medium confidence.",
            "source": "docs/dossier.md §7.4 [High that works were done, Med on totals]. Dates and figures unverified.",
            "verified": false
        },
        {
            "slug": "okpoko-general-hospital",
            "title": "Okpoko General Hospital",
            "type": "health",
            "project_status": "completed",
            "status_note": "Commissioned around March 2025",
            "funder": "Anambra State Government",
            "cost_ngn": null,
            "cost_note": null,
            "start_date": null,
            "target_date": null,
            "completed_date": null,
            "ward_code": null,
            "description": "Described as the area's first general hospital (\"Solution General Hospital\"), commissioned with the Federal Health Minister around March 2025. The state cites 102,643+ patients and 344 caesarean sections handled. These are the state's own figures.",
            "source": "docs/dossier.md §7.4, §8.3 [Med]. Dates and figures unverified.",
            "verified": false
        },
        {
            "slug": "atani-ozubulu-road",
            "title": "Atani-Ozubulu road and bridge",
            "type": "road",
            "project_status": "reported",
            "status_note": "Status unclear, verify. Reported ongoing in October 2025, and credited to the state as built in 2025",
            "funder": "Anambra State Government",
            "cost_ngn": 7640000000,
            "cost_note": "N7.64 billion, as reported.",
            "start_date": null,
            "target_date": null,
            "completed_date": null,
            "ward_code": null,
            "description": "About 11.37 km including a bridge, with contractor TAMAD and an 18-month schedule from early 2023. Vanguard reported it as ongoing in October 2025, while the Speaker of the State Assembly credited the state with building it in 2025. Completion status is unclear.",
            "source": "docs/dossier.md §8.1, §14. Dates and figures unverified.",
            "verified": false
        },
        {
            "slug": "atani-ekwusigo-road",
            "title": "Atani/Ekwusigo road",
            "type": "road",
            "project_status": "reported",
            "status_note": "Listed by the state as a Soludo-era project; status not stated",
            "funder": "Anambra State Government",
            "cost_ngn": null,
            "cost_note": null,
            "start_date": null,
            "target_date": null,
            "completed_date": null,
            "ward_code": null,
            "description": "Listed by the state among its projects for Ogbaru. No dates, cost or completion status are given in the dossier.",
            "source": "docs/dossier.md §8.1. Dates and figures unverified.",
            "verified": false
        },
        {
            "slug": "umunankwo-ossomala-bridge",
            "title": "Umunankwo-Ossomala bridge reconstruction",
            "type": "bridge",
            "project_status": "reported",
            "status_note": "Listed by the state as a Soludo-era project; status not stated",
            "funder": "Anambra State Government",
            "cost_ngn": null,
            "cost_note": null,
            "start_date": null,
            "target_date": null,
            "completed_date": null,
            "ward_code": null,
            "description": "Listed by the state among its projects for Ogbaru. No dates, cost or completion status are given in the dossier.",
            "source": "docs/dossier.md §8.1. Dates and figures unverified.",
            "verified": false
        },
        {
            "slug": "naval-outpost-road",
            "title": "Naval outpost access road (Onitsha-Odekpe)",
            "type": "road",
            "project_status": "completed",
            "status_note": "Commissioned 17 April 2026",
            "funder": "Private industrialist (public-private-community model)",
            "cost_ngn": null,
            "cost_note": null,
            "start_date": null,
            "target_date": null,
            "completed_date": "2026-04-17",
            "ward_code": null,
            "description": "A 1 km access road to the Nigerian Navy outpost, built by a private industrialist under a public-private-community model.",
            "source": "docs/dossier.md §7.6, §8.1 [Med]. Dates and figures unverified.",
            "verified": false
        }
    ]
}